Construction Project Management Glossary
Plain-language definitions of common construction project management terms.
- CPI (Cost Performance Index): a ratio of earned value to actual cost. Above 1.0 means the project is under budget for the work completed; below 1.0 means it is over. See Earned Value Management.
- Change Order: a formal, approved change to the scope, cost, or schedule of a contract after it is signed.
- DFOW (Definable Feature of Work): a measurable, physical part of a project used to track progress. See Definable Features of Work.
- EAC (Estimate at Completion): a forecast of the total cost of a project based on performance to date.
- EVM (Earned Value Management): a method of measuring project performance by comparing planned work, completed work, and actual cost. See Earned Value Management.
- Pay Application: a contractor's formal request for payment for work completed in a given period, typically monthly.
- Punch List: a list of outstanding items that must be corrected or completed before a project is considered finished.
- Retainage: a percentage of each payment withheld until a project is substantially complete, to ensure the work is finished to contract.
- RFI (Request for Information): a formal question submitted during construction asking for clarification on plans, specs, or scope.
- SPI (Schedule Performance Index): a ratio of earned value to planned value. Above 1.0 means the project is ahead of schedule; below 1.0 means it is behind.
- Submittal: a document, sample, or shop drawing submitted by a contractor for approval before work or materials are installed.
By invitation
Tell us what you build, and we'll show you the job.
Access is by invitation while the pilot runs. It takes a minute, and a person reads every one.
Sign-in opens with your account. Request access and we will send you the link.